Why did Voyage Status change from Completed to Closed?
Home > Operations FAQs > Why did Voyage Status change from Completed to Closed?
Problem
The status of multiple voyages changed from Completed to Closed, and it is not clear why.
Solution
The Voyage Status will not change unless a user has manually done this, either one-by-one or through the bulk closing option within the Voyage List, which requires the Close a Voyage Module Right.
To determine why this occurred, you can:
Look at the IMOS Audit Trail or IMOS - Audit Trail Report, and filter by Voyage and Vessel.
Add Last Modified On and Last Modified By columns to the Voyage List.
Check the Voyage Manager Revisions panel.
You cannot bulk update in reverse (i.e., change all Closed voyages to Completed); you must do that manually by opening the Voyage Manager.